Scheduled Production API Migration
Scheduled Maintenance Report for Aptible
Completed
The scheduled maintenance has been completed.
Posted Oct 12, 2015 - 23:05 EDT
Verifying
Verification is currently underway for the maintenance items.
Posted Oct 12, 2015 - 22:42 EDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 12, 2015 - 22:32 EDT
Update
The third and final phase of our production API migration will take place tonight (10/12) between 10:30pm and 11:30pm Eastern. While the APIs are down, our Git servers, dashboard.aptible.com, and aptible-cli functions will be unavailable. Customer apps and databases will be unaffected.
Posted Oct 12, 2015 - 21:50 EDT
Update
The second phase of our production API migration will take place tonight (9/30) between 10:30pm and 11:30pm Eastern. (The first phase ultimately resulted in zero downtime.) While the APIs are down, our Git servers, dashboard.aptible.com, and aptible-cli functions will be unavailable. Customer apps and databases will be unaffected.
Posted Sep 30, 2015 - 10:09 EDT
Scheduled
We will be migrating our production APIs to a new, upgraded environment between 10:30pm and 11:30pm Eastern tonight. During this time, all of our APIs may become unavailable. We will minimize the total downtime, but while the APIs are down, our Git servers, dashboard.aptible.com, and aptible-cli functions will be unavailable. Customer apps and databases will be unaffected, and will remain available throughout the migration.
Posted Sep 28, 2015 - 10:27 EDT